Cleveland Cascades complete retro-fit upgrade at Port Moody

Published by , Editor
Dry Bulk,


Cleveland Cascades has supplied two new Resitain valves to be retro-fit to the two existing potash loading chutes located in Port Moody, Vancouver (Canada).

A Cleveland Cascades engineer supported with the installation and commissioning of the new Resitain valves in Early March 2020.

The Resitain valve is fitted on the base of the carrier and is designed to close the exit of the Cascade chute when the loading operation has been completed.

A motor driven actuator operates two ‘trap doors.’ The doors hang vertical when the valve is open and swing together and seal the exit when closed.

A set of pre-adjusted limits are fitted and tested by Cleveland Cascades during the assembly of the units and then commissioned on site. These limits will be set at the fully open and fully closed positions.

Along with the installation of the Resitain valves, the chutes were also fitted with catenary cables for supplying power to the base of the chute to operate the valves, material detection probes and tilt switches.

Read the article online at: https://www.drybulkmagazine.com/material-handling/29042020/cleveland-cascades-complete-retro-fit-upgrade-at-port-moody/

You might also like

Bruks Siwertell secures new road-mobile ship unloader order in South Korea

Bruks Siwertell has secured an order for a next-generation Siwertell 10 000 S road-mobile ship unloader from South Korean operator, Incheon Northport Multipurpose Terminal. It will deliver environment-friendly cement handling and also ensure flexible, efficient operations at one of South Korea’s most important ports.

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Dry bulk shiploading news