Pattison Sand's new aggregates plant opens
Published by Nicholas Woodroof,
Editor
Dry Bulk,
This was a challenging demand considering most aggregates sites in the region typically focus on producing only a few products.
“We are very close to Pattison Sand, and spend a lot of time with them on-site brainstorming ideas and working together. When they have a problem we work tirelessly to find a solution that fits their needs and enables them to service their end market efficiently. When Pattison Sand presented the ambitious plan for their sand plant, our integrated solutions team worked with them to make it a reality,” said Eric Jones, Global Service Director of Comminution Aftermarket for Weir Minerals.
The facility, comprising both an underground and surface mine, is located on the Mississippi River. Processing highly abrasive materials combined with the physical diversity of the site presented a number of technical and engineering challenges. With an aggressive timeline of three months to deliver and commission the plant, Weir Minerals’ Integrated Solutions team was determined to meet Pattison Sand’s exacting demands.
“We develop these solutions with Weir Minerals through a lot of trials, successes and failures, and end up getting the results that we need to continue to survive in the marketplace. A lot of the options that other equipment manufacturers supply are standard and by the book. Weir Minerals has the ability to work with us to create solutions for our individual issues,” stated Chance Harvey, Director of Engineering, at Pattison Sand.
The site has a unique rail loadout setup where product is dispatched to customers as soon as gradation and quality data is approved. This meant Pattison Sand needed an efficient, dependable plant to meet stringent delivery requirements.
To make Pattison Sand’s vision a reality, Weir Minerals supplied a number of products to create two primary and secondary crushing stations. These included a Trio® TF5220 vibrating grizzly feeder, two Trio® EF3603 pan feeders and two Trio® TP450 cone crushers. Trio® scalping, incline and wet incline screens and as well as a Trio® TSW4432 fine material washer were also supplied. Full training and support was provided, with Weir Minerals regularly on site to help Pattison Sand optimise their entire process and achieve the desired result.
The flexibility of the custom built plant has allowed Pattison Sand to operate more efficiently, exceed production target and increase their product range. Since commissioning the plant, Pattison Sand has been able to produce 500 – 800 tph of consistently high-quality aggregate material, which equates to around 2.5 million raw tpy. Four hoppers provide a loadout rate of 500 tph enabling Pattison Sand to produce a diverse range of products and still meet demanding customer delivery schedules.
“When customers purchase Trio® products they are buying years of experience from people within an organisation that is dedicated to the industry and its customers. We constantly strive to be closer to our customers. It’s not always perfect, but we work through projects together and are honest with each other. It’s that transparency and working with customers like Pattison Sand which really drives the end solution,” stated Eric Jones.
Kyle Pattison, owner of Pattison Sand, stated: “Pattison Sand Company and Weir Minerals have a good working relationship because of the successes we've had solving problems and delivering good quality products on time. It’s human nature to interact more with the company that helps solve your problems and provides good value. Those that don’t, you don’t go back and talk to them.”
Read the article online at: https://www.drybulkmagazine.com/dry-bulk/05022019/pattison-sands-new-aggregates-plant-opens/