A major upgrade of CBH’s Mingenew receival site has been completed, delivering storage, and improved reception infrastructure ahead of the 2026/27 harvest.
The project has delivered a further 270 000 t of open bulkhead storage, increasing the site’s total capacity to 710 000 t. As the largest upcountry reception site in Area 2, Mingenew plays an important role in the movement of grain through the Geraldton Zone and into CBH’s export supply chain. The upgraded site received its first grain on 5 October, with canola delivered into one of the seven open bulkheads.
The site upgrades include: Seven open bulkhead storages, providing 270 000 tonnes of storage capacity; two new 500 tph auger pit and conveyor inloading systems; new dual-spear Type 11 sample hut, increasing the number of available sampling spears from two to three; improved site drainage, power connectivity, and amenities. In addition, a new 24-bed accommodation facility has been completed at Mingenew, providing modern, self-contained accommodation to support CBH’s operational and seasonal workforce in Mingenew. The facility includes private ensuite rooms, kitchen, dining, laundry, and common areas, along with parking and supporting infrastructure.
Geraldton Zone Manager Colette Newton said the upgrade would help meet growing harvest demands.
“For growers, that means greater confidence the site can continue to perform during larger and faster harvests, helping reduce delays and minimise standing crop risk at peak times,” said Newton.
Head of Network Planning, Nelson Aylmore, said the completed project strengthened Mingenew’s role within the Geraldton Zone network.
“Mingenew is a critical site in our Geraldton Zone network, and this investment is about ensuring we can continue to support growers with reliable, efficient receival capacity now and into the future,” said Aylmore. “This investment supports our Path to 2033 Strategy by ensuring our network keeps pace with production and continues to provide reliable and efficient service for growers.”